Investors in AI data centers face growing financial risks as delays in securing electricity connections threaten project timelines, valuations and investment returns, according to a new study by IQ-EQ and the Sustainable Real Estate Forum (SREF).
The study, “Powering Intelligence: Can Data Centres and the Energy Transition Coexist?” warns that investors may be valuing data center assets as having secured power even though grid connections remain uncertain. In Europe’s major data center markets, securing a grid connection can take seven to 10 years, compared with two to three years to construct a facility.
The discrepancy creates risks for investors financing projects based on anticipated AI demand before the necessary power infrastructure is in place.
“If power is the constraint, energy geography becomes part of the investment thesis