Publications

Energy - JULY 6, 2020

To read this full article you need to be subscribed to Newsline.

Sign in Sign up for a FREE subscription

Developers cancel $8b Atlantic Coast Pipeline

by Andrea Zander

Dominion Energy and Duke Energy have canceled their Atlantic Coast Pipeline project, a natural gas pipeline that was to stretch hundreds of miles across West Virginia, Virginia and North Carolina, citing “legal uncertainty.”

Despite last month's overwhelming 7-2 victory at the U.S. Supreme Court, which vindicated the project and decisions made by permitting agencies, recent developments have created an unacceptable layer of uncertainty and anticipated delays for ACP.

Specifically, the decision of the U.S. District Court for the District of Montana overturning long-standing federal permit authority for waterbody and wetland crossings (Nationwide Permit 12), followed by a Ninth Circuit ruling on May 28 indicating an appeal is not likely to be successful, are new and serious challenges. The potential for a Supreme Court stay of the district court's injunction would not ultimately change the judicial venue for appeal nor decrease the uncertainty associated with an even

Forgot your username or password?