Bridging Pennsylvania Partners (BPP), a consortium consisting of Macquarie Capital and S&B USA Concessions, has reached financial close with the Pennsylvania Department of Transportation (PennDOT) for the first package of a major public-private partnership (P3) bridge project.
The project includes the design, build, financing and maintenance of the bridges, in addition to related roadway and supporting infrastructure.
The first package of the Major Bridge P3 program will replace six bridges in critical need of replacement across the commonwealth of Pennsylvania: I-81 Susquehanna, I-80 Nescopeck Creek, I-78 Lenhartsville, I-80 Lehigh River, I-80 Canoe Creek and I-80 North Fork. Construction is set to begin in September 2023 and will be completed between September 2027 and June 2028.
The program includes a total of nine bridges — three of which are to be delivered in a second package. Macquarie Capital and S&B USA Concessions will work with PennDOT to de