Acciona Energia has signed a contract for the construction of four renewable energy plants in Chile, with an investment of $610.65 million.
Construction is already under way of the 183-megawatt San Gabriel wind farm in Renaico. The $300 million project is expected to be online by 2020.
Acciona is also planning to build the $150 million, 87-megawatt Tolpan wind project close to San Gabriel.
The other two projects include the construction of the 62-megawatt Almeyda solar farm on land at Diego de Almagro in the Atacama region, and the 64-megawatt Usya photovoltaic plant in Calama in the Antofagasta area.
The solar plants will supply electricity to the National Mining Company of Chile.